ITA1 Anchor Platform Module Fabrication

Location

Kearl In Pit Tailings Area 1 (ITA 1)

Date

June 2021 - May 2022

Fabricated three floating Anchor platforms. The job consisted of three floating modules including a roof structure, piping, instrumentation, electrical, mooring design and ballasting. Job was completely fabricated, trial assembled, FAT tested and painted in house. Modules size 24 x 24 x 60ft x 100,000 kg ea., roof structure oversized and shipped loose.